API API-SIEE Exam Syllabus Topics:
| Section | Objectives |
|---|---|
| Electrical Inspection Tools and Test Equipment | |
| Terms and Definitions | |
| Liquid-Immersed Transformers | - Design and Construction - Industry Codes and Standards |
| Examination Methods, Tools and Equipment | - Typical Electrical Testing Techniques - Surface Preparation and Coatings Inspections - Dimensional Inspections - Visual Inspections - Functional Testing |
| Electrical Induction Motors | - Design and Construction Standards - Motor Testing - Materials of Construction |
| Motor Control Centers Low to Medium Voltage | - Amp Capacity - Design and Construction Standards - Enclosures Types - Ground Bus - Main Isolating Switch - Main Feeder Cable Entry Compartment - Materials of Construction - Circuit Breakers |
| Source Inspection Performance | - Report Writing Nonconformance and Deviations - Inspector Conduct and Safety - Review of Project Documents |
| Source Inspection Management Program | |
| Equipment Risk Assessment | - Report Review - Development of a Source Inspection Project Plan - Development of Inspection and Test Plans |
| Switchgear Low and Medium Voltage | - LV AC Switchgear Grounding - Design and Construction - Ratings Interlocks - Bus Compartment - Wiring - Switchgear Section Compartments - LV Switchgear Grounding - Switchgear Compartment Doors - Voltage Transformers - Metering - Current Transformers - Control Power Transformers - Housing Frames and Enclosure Compartment - Electric Tie Breakers - Circuit Breakers |
| Electrical Skid Mounted Equipment | - Equipment Grounding - Industry Codes and Standards - Purged and Pressurized Equipment in Classified Locations - Electrical Equipment for Hazardous Classified Locations - AC Control Wiring - Materials of Construction - Cable Support Systems |
API-SIEE Exam FAQs: Honest Answers
The API Source Inspector Electrical Equipment blueprint has 11 domains, led by Terms and Definitions, Liquid-Immersed Transformers, Switchgear Low and Medium Voltage. Think of the weightings as the vendor's hint about where points concentrate — plan your hours accordingly. The complete outline above lists every subtopic.
Passing the API-SIEE exam earns you the ICP Programs certification at the Professional level — API's official verification of your skills. It's considered important because it's genuinely difficult, which is exactly why it carries weight with employers. Related credentials include API SIEE - Source Inspector Electrical Equipment.
110 questions, 100 scored questions in 195 minutes. That combination rewards candidates who've trained their pace, not just their memory — so before the real thing, run full timed sessions in the PracticeVCE engine, practice flagging hard questions instead of fighting them, and learn what your sustainable per-question rhythm feels like.
Delivery is instant: successful payment triggers an automatic email with your product, arriving in about a minute — install on unlimited computers, and if 2 hours pass with nothing, our 24/7/365 customer service will fix it fast. The guarantee: take the corresponding API-SIEE exam within 60 days of purchase, and if you fail, submit a scanned enrollment slip plus the official Score Report PDF within 2 days of the exam for a 100% refund processed within 7 days. Exclusions: exams within 3 days of purchase, name mismatches between candidate and payer, and free or expired products. Prefer a swap? Take two equal-value exam products free, updates intact.
Prequalification is required. Minimum electrical experience depends on education and background, ranging from 2 to 5 years. Before paying any registration fee, verify the current criteria on the official exam page — since vendors do revise their rules.
The official fee is USD $380 member / USD $500 non-member, with Set passing scaled score required to pass. Both numbers matter more together: the fee is per attempt, so every retake costs the full amount again. Drilling the 113 practice questions from PracticeVCE until you're comfortably past the mark is the fiscally sound approach.
Yes — the free demo gives you several real questions and answers from the set, so you can see whether it interests you and helps you before spending anything. Once you buy, updates are free for 365 days — new versions are mailed to you automatically — and an expired update period renews at 50% off.
API Source Inspector Electrical Equipment Sample Questions:
According to NETA, for low voltage cables a visual inspection must verify that:
- A. the shield on power cables is properly grounded.
- B. connections are in accordance with the single-line diagram.
- C. color codes comply with IEEE requirements.
- D. all cables are connected to terminals via ring tongue lugs.
Correct Answer: B 🗳️
Explanation: Only visible for PracticeVCE members. You can sign-up / login (it's free).
Metallic shielding components such as tapes, wires, or braids shall be connected to a:
- A. low voltage ceramic insulator.
- B. center tap of a transformer.
- C. low voltage connector.
- D. equipment grounding busbar.
Correct Answer: D 🗳️
Explanation: Only visible for PracticeVCE members. You can sign-up / login (it's free).
During the course of manufacturing the supplier/vendor may propose design changes that could impact cost, schedule and/or quality. In such cases, the source inspector should:
- A. prepare a summary of the changes made for inclusion in their report and subsequent action by the purchaser.
- B. prepare a cost/benefit analysis in order to justify their acceptance or rejection of the proposed changes.
- C. request that the supplier/vendor develop a cost/benefit analysis for review and approval by the inspector.
- D. request that the supplier/vendor propose such changes in writing for review by the purchaser.
Correct Answer: D 🗳️
Explanation: Only visible for PracticeVCE members. You can sign-up / login (it's free).
Machine vibration measurement using non contacting probes are taken:
- A. on horizontal, vertical and the axial directions on the bearing housings.
- B. on the shaft at 1.2 times the running speed.
- C. on horizontal, vertical and the axial directions on the baseplate.
- D. on the frame during residual unbalance with the feet unclamped.
Correct Answer: A 🗳️
Explanation: Only visible for PracticeVCE members. You can sign-up / login (it's free).
Final inspection and shipping preparations of switchgear typically consists of verifying all of the following except:
- A. all items on the manufacturer's QC checkout are signed off.
- B. all final manufacturing and drawing issues are closed.
- C. correct engraving of unit and master nameplates.
- D. visual inspection of packaging requirements.
Correct Answer: B 🗳️