NEW QUESTION # 65
Which TWO statements describe a purpose of the business case?
1) To define the acceptance criteria for what the project must deliver.
2) To transfer responsibility for the work to the appropriate delivery team.
3) To document how significant risks will affect the expected project benefits.
4) To outline how and when the anticipated benefits can be measured.

  • A. 2 and 3
  • B. 1 and 2
  • C. 1 and 4
  • D. 3 and 4

Answer: D


NEW QUESTION # 66
Which is a purpose of the 'controlling stage' process?

  • A. To establish whether the project is complete
  • B. To report stage progress to the project board
  • C. To execute and deliver the project product
  • D. To draft the plan for the next stage's work

Answer: B

Explanation:
Reference:
%20remains%20within%20tolerance.&text=Risks%20and%20issues%20are%20kept%20under%20control


NEW QUESTION # 67
When should the project canvas be BOTH updated and used to assess whether the intended benefits have been or will be realized?

  • A. At the end of each delivery stage
  • B. At the end of the final delivery stage
  • C. At the end of the initiation stage
  • D. At the end of the pre-project stage

Answer: A

Explanation:
Agile Foundation guidance describes the project canvas as a living, lightweight artifact that supports alignment, transparency, and ongoing benefit realization throughout the project lifecycle. It should not be treated as a one-time planning document. The correct point at which the project canvas should be both updated and used to assess whether intended benefits have been or will be realized is at the end of each delivery stage, making option C the correct answer.
Agile and PRINCE2 Agile approaches emphasize incremental delivery and continuous validation of value. Each delivery stage produces usable outputs or increments that can be reviewed against expected outcomes and benefits. Updating the project canvas at the end of each delivery stage allows the team and stakeholders to reflect on what has actually been delivered, what has changed, and whether assumptions made earlier are still valid. This includes reassessing benefits, risks, stakeholders, and priorities based on real evidence rather than predictions.
Option A, the end of the pre-project stage, is too early, as no meaningful delivery has occurred to assess benefits. Option B, the end of initiation, focuses on planning and setup rather than value realization. Option D, the end of the final delivery stage, is too late because it limits opportunities to adapt if benefits are not being realized as expected.
Agile Foundation documents stress the importance of frequent inspection and adaptation. By reviewing and updating the project canvas at the end of each delivery stage, teams can make informed decisions about continuing, pivoting, or stopping work. This supports effective governance while preserving agility. Regular benefit assessment ensures that the project remains aligned with business objectives and continues to justify investment, reinforcing Agile's focus on value delivery rather than simply completing planned activities.


NEW QUESTION # 68
Which PRINCE2 principle should be followed in order to engage the business, user and supplier stakeholder interests?

  • A. Tailor to suit the project
  • B. Defined roles and responsibilities
  • C. Continued business justification
  • D. Learn from experience

Answer: B

Explanation:
Reference: https://prince2.wiki/principles/defined-roles-and-responsibilities/#:~:text=PRINCE2%20states%
20that%20a%20project,Business%20sponsors%2C%20Users%20and%20Suppliers


NEW QUESTION # 69
What term is used to describe boards that display what work needs to be completed for people working on a project?

  • A. Glad! Sad! Mad!
  • B. Highlight report
  • C. Information radiator
  • D. Work in progress limit

Answer: B

Explanation:
Reference: https://publications.axelos.com/prince2agile2016/content.aspx?
page=pra_190&showNav=true&expandNav=true


NEW QUESTION # 70
How does AI align with PRINCE2 Agile's iterative approach?

  • A. By defining the Definition of Done
  • B. By reducing the need for frequent testing
  • C. By offering predictive insights to respond to change
  • D. By reducing the need for continuous feedback

Answer: A

Explanation:
Within Agile Foundation guidance and PRINCE2 Agile alignment, the Definition of Done (DoD) plays a critical role in supporting an iterative approach to delivery, making option C the correct answer. PRINCE2 Agile combines the governance strengths of PRINCE2 with the flexibility of Agile delivery, and iteration is central to how value is delivered incrementally. The DoD provides a shared and consistent understanding of what it means for work to be complete at the end of each iteration.
The iterative approach in PRINCE2 Agile relies on delivering small, usable increments frequently. The Definition of Done ensures that every increment meets agreed quality standards before it is considered complete. This supports transparency, predictability, and trust, which are essential for iterative delivery. Without a clear DoD, teams risk producing partially finished work that cannot be reviewed, tested, or released, undermining the benefits of iteration.
Option A is incorrect because Agile and PRINCE2 Agile emphasize continuous feedback as a core mechanism for learning and adaptation. Option B, offering predictive insights, is not a defining element of PRINCE2 Agile's iterative approach; Agile focuses more on empirical feedback than prediction. Option D is also incorrect because frequent testing is encouraged, not reduced, in iterative Agile delivery.
Agile Foundation documents emphasize that the DoD acts as a quality gate that supports incremental progress while maintaining control. It aligns delivery teams and stakeholders on expectations and ensures that each iteration produces a potentially usable output. In PRINCE2 Agile, this alignment allows teams to work autonomously within defined tolerances while still meeting governance and assurance requirements. By clearly defining what "done" means, the DoD strengthens the iterative cycle of build, review, learn, and adapt, which is fundamental to Agile and PRINCE2 Agile working together.


NEW QUESTION # 71
Which statement is CORRECT with respect to the management of risk using PRINCE2 Agile?

  • A. It should always be carried out formally
  • B. It should always be appropriate to the needs of the project
  • C. It should always be carried out informally
  • D. It should always be addressed during the daily stand-ups

Answer: B


NEW QUESTION # 72
Which artifact is used to describe the project's major products in the form of epic user stories?

  • A. Project backlog
  • B. Product backlog
  • C. Project dashboard
  • D. Release map

Answer: A

Explanation:
The Project Backlog is the artifact used to describe the project's major products in the form of epic user stories. Epic stories are large, high-level user stories that capture significant features or product components that may later be decomposed into smaller, more detailed user stories in the product backlog.
The Project Backlog provides a strategic view of what the project intends to deliver and supports planning at the project level, including releases and stages. It bridges the gap between business requirements and team-level delivery.
The Product Backlog (C) contains detailed user stories ready for development but is typically more granular. The Release Map (B) plans releases and iterations but does not list epic stories. The Project Dashboard (A) is a reporting tool, not a repository of requirements.
The use of epic user stories in the project backlog aligns with agile practices for managing scope and enables incremental delivery aligned with business priorities.


NEW QUESTION # 73
Which PRINCE2 principle should be followed in order to engage the business, user and supplier stakeholder interests?

  • A. Tailor to suit the project
  • B. Defined roles and responsibilities
  • C. Continued business justification
  • D. Learn from experience

Answer: B


NEW QUESTION # 74
Which statement about the 'be on time and hit deadlines' target is CORRECT?

  • A. It allows change to be handled dynamically
  • B. It helps with planning dependencies within a project
  • C. It ensures that the level of quality is protected
  • D. It is achieved by keeping the delivery teams stable

Answer: B


NEW QUESTION # 75
Which describes the Scrum Master role in Scrum?

  • A. It is authorized to run the project on a day-to-day basis on behalf of the project board
  • B. It is responsible for ensuring that product backlog items are clearly expressed on the product backlog
  • C. It is servant-leadership to help everyone change their interactions to maximize the value created by the team
  • D. It is empowered to organize and manage its own work to create a valuable, useful increment every sprint

Answer: B


NEW QUESTION # 76
According to PRINCE2 Agile, which form of communication shows that a team is vibrant and interactive?

  • A. Using visualization to display information
  • B. Using email to document discussions
  • C. Using social media to reach more people
  • D. Using meeting minutes to share decisions

Answer: A

Explanation:
Reference: https://publications.axelos.com/PRINCE2Agile2016/content.aspx?
page=pra_165&showNav=true&expandNav=true


NEW QUESTION # 77
Which of the following is used to monitor progress?

  • A. Swarming
  • B. Burn-down chart
  • C. Delegation matrix
  • D. T-shirt sizing

Answer: B

Explanation:
The burn-down chart is a visual tool used in agile to monitor progress by tracking the remaining work against time. It provides teams and stakeholders with a clear, real-time view of project status and forecast completion, allowing for early identification of potential delays or bottlenecks.
The delegation matrix (A) defines authority, swarming (B) is a team collaboration technique, and t-shirt sizing (C) is an estimation method, none of which directly monitor progress.
Reference: PRINCE2 Agile Foundation Version 2, Section 7.1 "Progress Practice," and PRINCE2 Agile Study Guide, Chapter 7.


NEW QUESTION # 78
What is a role of personas in the 'business case' practice?

  • A. To identify and articulate specific user benefits
  • B. To differentiate between product versions
  • C. To group users based on demographic data
  • D. To ensure project timelines are met

Answer: A

Explanation:
Personas in PRINCE2 Agile serve as fictional, archetypal users representing the needs, behaviors, and goals of real users. In the business case practice, personas are used to identify and articulate specific user benefits.
This ensures the project focuses on delivering value that meets the actual needs of different user groups.
By understanding personas, teams can tailor product features and prioritize requirements that provide meaningful benefits, thereby strengthening the business case and increasing stakeholder buy-in. Personas help clarify who will use the product, what problems they face, and how the solution delivers value.
Personas go beyond demographic grouping (A); they are detailed profiles including motivations and pain points. They do not relate directly to timelines (B) or product version differentiation (D).
Using personas aligns with agile principles of customer focus and continuous stakeholder engagement embedded in PRINCE2 Agile.
Reference: PRINCE2 Agile Foundation Version 2, Section 7.1 "Using Personas in Business Case," and PRINCE2 Agile Study Guide, Chapter 7.


NEW QUESTION # 79
How does PRINCE2 Agile describe Scrum?

  • A. Scrum is a project management framework
  • B. Scrum is agile and agile is Scrum
  • C. Scrum is an IT method
  • D. Scrum is the most well-known agile framework

Answer: D


NEW QUESTION # 80
Which is typically used in agile when estimating detailed requirements during sprint planning?

  • A. Rationalism
  • B. Visioning
  • C. T-shirt sizing
  • D. Trading

Answer: A


NEW QUESTION # 81
Which statement about the waterfall methodology definition is CORRECT?

  • A. It delivers products more frequently in shorter phases
  • B. It prevents earlier phases of development being revisited
  • C. It focuses on responding to changing requirements
  • D. It uses an iterative and incremental approach

Answer: B


NEW QUESTION # 82
Which is a typical characteristic of 'business as usual' work?

  • A. It is executed by program management
  • B. It requires a specific dedicated project manager
  • C. It is delivered by an established team
  • D. It is delivered by a temporary team

Answer: C

Explanation:
Reference: https://www.prince2primer.com/prince2-agile-overview-part-1/


NEW QUESTION # 83
Why is Lean Startup included in the 'starting up a project' process in PRINCE2 Agile?

  • A. Because it explains how a small company can grow using traditional technologies
  • B. Because running a project and setting up a new business are the same
  • C. Because it is designed to manage projects, delivering products in timeboxes
  • D. Because it enables agile to be used in challenging and uncertain situations

Answer: D


NEW QUESTION # 84
Which of the following integrated elements defines who is working on the project and who is affected by the project?

  • A. The "people" element
  • B. The PRINCE2 practices
  • C. The project context
  • D. The PRINCE2 processes

Answer: A

Explanation:
Agile Foundation guidance, aligned with PRINCE2 Agile concepts, explains that integrated elements are used to describe different aspects of how a project is structured and delivered. Among these elements, the "people" element specifically defines who is working on the project and who is affected by the project, making option D the correct answer.
The people element focuses on roles, responsibilities, relationships, and stakeholders involved in the project. It identifies not only the delivery team members but also sponsors, users, customers, suppliers, and any individuals or groups impacted by the project's outcomes. Agile and PRINCE2 Agile both emphasize that successful delivery depends heavily on people, collaboration, and clear accountability. Understanding who is involved and affected ensures effective communication, engagement, and decision-making throughout the project lifecycle.
Option A, the project context, describes the environment in which the project operates, including organizational, regulatory, and external factors, but it does not specifically define who is involved. Option B, the PRINCE2 practices, focuses on areas such as risk, quality, plans, and progress, providing guidance on what needs to be managed rather than who is involved. Option C, the PRINCE2 processes, outlines the flow of activities and decision points during the project, not the people performing or impacted by them.
Agile Foundation documents stress that Agile delivery is people-centric. Self-organizing teams, empowered roles, and active stakeholder involvement are core to Agile success. The people element supports this by ensuring clarity around roles, expectations, and collaboration pathways. By clearly defining who is working on the project and who is affected by it, teams can build trust, manage stakeholder needs effectively, and adapt to change more smoothly. This alignment of people with purpose and value delivery is central to both Agile principles and PRINCE2 Agile integration.


NEW QUESTION # 85
Which statement about the waterfall methodology definition is CORRECT?

  • A. It states that deadlines should not be moved
  • B. It has distinct goals for each stage of development
  • C. It promotes the use of experiments carried out in a scientific way
  • D. It is a behavior that involves making things transparent

Answer: B


NEW QUESTION # 86
......