NEW QUESTION 67
An operator notice a pipe off its support, what should be done?

  • A. Contact maintenance personnel for immediate repair
  • B. Report the situation to engineering or inspection personnel
  • C. Keep a record of the situation for future reference
  • D. Ignore the situation

Answer: B

 

NEW QUESTION 68
Is the thickness range on the WPS supported by the PQR?

  • A. No
  • B. Re qualification is required by API 570
  • C. Re qualification is required by ASME Section V
  • D. Yes

Answer: A

 

NEW QUESTION 69
Who has the responsibility for qualifying welding procedures?

  • A. Each contractor
  • B. Each subcontractor
  • C. Each employer
  • D. Each welder

Answer: C

 

NEW QUESTION 70
The preheat zone shall extend beyond each edge of a pipe weld

  • A. 3T
  • B. 2"
  • C. 2T
  • D. 1"

Answer: D

 

NEW QUESTION 71
The repair organization shall maintain records of welding procedures and welder qualifications and make the records available to the inspector_____.

  • A. after completion of welding
  • B. when the repair organization releases the information
  • C. prior to the start of welding
  • D. any time during welding

Answer: C

 

NEW QUESTION 72
Appropriate permanent and progressive records on each piping system shall include.

  • A. system service; classification; identification numbers
  • B. all jurisdictional requirements
  • C. original heat and batch numbers
  • D. all original construction data

Answer: A

 

NEW QUESTION 73
Excessive cyclic stresses that are well below the static yield strength of the material result in.

  • A. material failure
  • B. fatigue cracking
  • C. failure cracking
  • D. creep cracking

Answer: B

 

NEW QUESTION 74
API 570 covers the inspection of__________.

  • A. In-service piping
  • B. new construction
  • C. In-service vessels
  • D. new tank construction

Answer: A

 

NEW QUESTION 75
Is the attached PQR properly qualified?

  • A. No, because peening is allowed by ASME B31.3
  • B. No, because there are not enough tensile tests
  • C. Yes
  • D. No, because RT is not allowed during PQR qualification

Answer: B

 

NEW QUESTION 76
provides general requirements and detailed assessment procedures for specific types of degradation that are referenced in API 570.

  • A. ASME 816.5
  • B. API 598
  • C. API 653
  • D. API RP 579

Answer: D

 

NEW QUESTION 77
What is the pressure design thickness of NPS10A516 Gr.65 Type 22 pipe that operateat 1200psig/750°F

  • A. Not enough in formation given
  • B. 0.928"
  • C. 0.432"
  • D. 0.46"

Answer: D

 

NEW QUESTION 78
The liquid penetrant examination method is an effective means for detecting.

  • A. surface discontinuities of a weld
  • B. internal discontinuities of a weld
  • C. subsurface discontinuities of a weld
  • D. both Internal and surface discontinuities of a weld

Answer: A

 

NEW QUESTION 79
Penetrameters are normally placed on the side of the part being examined.

  • A. film
  • B. source
  • C. reverse
  • D. weld

Answer: B

 

NEW QUESTION 80
Without the benefit of an impact test, what is the minimum operating temperature for A-106 Grade B material used in a Category D Fluid Service?

  • A. -20°C
  • B. -29°F
  • C. -20°F
  • D. 0°F

Answer: C

 

NEW QUESTION 81
Welding procedures qualified by may be used, subject to the specific approval of the inspector

  • A. others
  • B. the use of API 1104 qualified procedures
  • C. the use of AWS pre qualified, D1.1 type procedures
  • D. the employer

Answer: A

 

NEW QUESTION 82
can cause flame detectors used to indicate a furnace or boiler fire to give false indications on control panels.

  • A. Radiographic inspection
  • B. Piping alterations in the shop
  • C. Welding or related repairs on piping
  • D. Ultrasonic inspection

Answer: A

 

NEW QUESTION 83
Geometric unsharpness of the radiograph of a component under 2" th1ck shall not exceed

  • A. 0.050"
  • B. 0.040"
  • C. 0.020"
  • D. 0.030"

Answer: C

 

NEW QUESTION 84
A visual examination of performance test coupons shall_______.

  • A. show complete joint penetration and complete fusion of weld metal and base metal
  • B. be allowed one 5/32" crater crack
  • C. show no more than 1/3t non fusion
  • D. show no more than 1/3t inadequate penetration

Answer: A

 

NEW QUESTION 85
More than one contractor, manufacturer or installer may simultaneously qualify a welder. In such case, each participating organization shall be represented by during the test.

  • A. A certified welding inspector
  • B. A welding engineer
  • C. A responsible employee
  • D. The welder's supervisor

Answer: C

 

NEW QUESTION 86
In a piping circuit, which of the following does not routinely have thickness measurements taken?

  • A. Fittings
  • B. Dead legs
  • C. Valves
  • D. Straight Run Pipe

Answer: C

 

NEW QUESTION 87
Besides ultrasonic instruments, what other method can be used to determine thickness measurements?

  • A. ET
  • B. AET
  • C. RT
  • D. MT

Answer: C

 